30/12/2021

Photo report from the investment

30/11/2021

Photo report from the investment

21/10/2021

Building occupancy permit

13/09/2021

Construction progress

  • Works on painting the walls of the staircase in part A of the building are in progress
  • In the course of work on the flooring resin in the garage
  • There are separate storage rooms in a part of the garage
  • Final works of laying stoneware pedestals in parts A and B of the building
26/08/2021

Construction progress

-Work on the entrance to the garage has been completed

– Greenery works have been completed

– The elevators were accepted by UDT in parts A and B of the building

– A fence has been installed on the side of ul. Kasztelańska

– Intercoms were installed in both staircases, parts A and B of the building

– Works on the development of the investment area have been completed

13/07/2021

Construction progress

– Resin coatings were made on balconies in part B of the building
– White electrical installation was carried out in the apartments (sockets, switches) in part B of the building
– Currently, carpentry work is underway on the staircase in part B of the building (finishing door portals, apartment doors and elevator)
– 100% aluminum joinery was installed in part B of the building (including the vestibule)
– The staircase lighting lamps are being installed in part B of the building
– The attic insulation has been completed with mineral wool and the attic casing with a plasterboard on the frame in part A of the building
– The plastering of walls and ceilings in the premises has been completed. Ground floor – 3rd floor in part A of the building
– The surfaces of walls and ceilings in flats in part A of the building are primed with paint
– Currently, finishing works are underway (plastering, plasterboard structures) in the staircase in part A of the building
– Entrance doors to the premises in part A of the building have been installed
– Balcony railings were installed in part A of the building
– The painting of the facade of part A of the building has been completed
– Resin coatings were made on balconies on the level of 1-3 floors of the building and in the garbage can in part A of the building
– The assembly of the elevator in part A of the building has been completed (procedures for the elevator acceptance by UDT are in progress)
– Installation of local heaters in apartments in part A of the building is in progress
– White electrical assembly in the apartments in part A of the building is in progress
– Water and sewage works completed. , What. and hydrant installation
– Performance tests of hydrants in the garage were carried out with a positive result
– Lighting of the garage and the entrance to the garage was made (target lamps with motion sensors installed)
– The entrance gate to the garage has been installed
– Works related to the development of the area around the buildings have been started (i.e. paving works – sidewalks, bands; greenery works – surface drainage of the ceiling above the garage, rain drains, geotextiles, fertilization of fertile soil, fencing works)

24/05/2021

Construction progress

– Porcelain floors in the staircase were made, along with the facing of stair steps and the arrangement of pedestals in part B of the building

– Water meters and heat meters have been installed in water and sewage installation risers and what in part B of the building

– The assembly of the elevator has been completed, preparations are underway for acceptance by the Office of Technical Inspection in part B of the building

– The external facade of part B of the building was cleaned, primed and painted

– Residential changes related to bricklaying partition walls in part A of the building have been completed

– Water and sewage installations completed. and what. in apartments in part A of the building

– Installation of electrical installations inside the premises in part A of the building has been completed

– Cement screeds on the 3rd floor have been completed. – Ground floor in part A of the building

– Finishing works of the premises are in progress – plastering ceilings and walls, making window frames from plasterboard, etc. in part A of the building

– The attic is partially insulated with mineral wool along with the installation of the frame for the construction of the plasterboard in part A of the building

– Installation of an elevator in progress – a passenger lift in part A of the building

– An energy connection with a cable connection has been made. Final acceptance by the Power Plant is in progress

– Troughs and power cables have been laid for the Main Switchboard in the garage from the cable connection

– Insulation of the walls of staircases in the garage with mineral wool along with spraying with thin-layer plaster

– Insulation with polystyrene has started from the bottom of the projecting parts of building A and the connector

– A rainwater flow regulator was installed in the external rainwater well

08/04/2021

Construction progress

– External balcony railings were installed in part B of the building

– Roofing works have been completed – roofing with aluminum sheet with flashings, gutters and downspouts in part B of the building

– An external lightning protection system was installed in part B of the building

– A set of accessories was installed on the roof, such as fans, air vents, lightning protection masts, chimney sweeps, snow guards and a roof hatch in part B of the building

– Entrance doors to the premises in part B of the building have been installed

– The filling of internal walls and GK constructions in part B of the building has been completed

– The putty walls were painted with white priming paint in the apartments in part B of the building

– The aluminum door of the main entrance to part B of the building has been installed

– Local heaters were installed in part B of the building

– Roofing with aluminum sheet in part A of the building has been completed

– Sheet metal work, gutters and downspouts in part A of the building were completed

– An external lightning protection system with lightning protection masts was installed on the roof in part A of the building

– A set of accessories was installed on the roof, such as fans, exhaust vents, roof hatch, chimney sweeps and snow guards in part A of the building

– Water and sewage risers were made. in part A of the building

– Mechanical ventilation risers in part A of the building

– Partition walls of the ground floor, 1st floors, 2 floors, shafts and bathrooms, 3 floors and attic in part A of the building were built

– Water and sewage installation work has commenced. And what. in apartments in part A of the building

– Electrical works have commenced in the apartments in part A of the building

01/03/2021

Construction progress

01/02/2021

Construction progress

05/01/2021

Construction progress

07/12/2020

Construction progress

03/11/2020

Construction progress

14/10/2020

Construction progress

16/09/2020

Construction progress

13/09/2020

Construction progress

21/08/2020

Construction progress

17/06/2020

Construction progress

25/05/2020

Construction progress

10/02/2020

Construction progress

 • The foundation slab is concreted

 • Garage walls are being built

 • The excavation under building A is completed

 • A square timber band in the Berlinka-type wall is made

 • The entire excavation was secured

 • A layer of lean concrete has been made

 • The construction of foundation wells is in progress

21/01/2020

Construction progress

• Completed:

– foundation wells under the foundation slab

– a layer of lean concrete

– a layer of horizontal insulation

– the bottom plate of the lift shaft

– foundation slab reinforcement

13/12/2019

Ground works

  • A set of CFA piles was made along the building’s outline for the Berlin wall as protection of the excavation for the building
  • Berlin wall was made in axes 1 / A-E, in axis E / 1-4 (along the existing building), in axis A / 1-4 3
  • An excavation was made for the building’s garage in level -1 in area A-E / 1-5

Urba CHECK OUR OTHER DEVELOPMENTS

Wille Tetmajera
Wille Tetmajera

Location: Bronowice

CHECK
Lifehub
Lifehub

Location: Krowodrza

CHECK

Ask for the price

Show privacy policy

* - fields required

Thank you!

The form has been sent. The Sales Department will contact you as soon as possible.

Back to the site

Cookies

On this website use cookies to provide you with services at the highest level, including in a manner tailored to individual needs. Using the site without changing the settings for cookies means that they will be placed on your device. You can change your cookie settings at any time. More details in our Privacy Policy