-Work on the entrance to the garage has been completed
– Greenery works have been completed
– The elevators were accepted by UDT in parts A and B of the building
– A fence has been installed on the side of ul. Kasztelańska
– Intercoms were installed in both staircases, parts A and B of the building
– Works on the development of the investment area have been completed
– Resin coatings were made on balconies in part B of the building
– White electrical installation was carried out in the apartments (sockets, switches) in part B of the building
– Currently, carpentry work is underway on the staircase in part B of the building (finishing door portals, apartment doors and elevator)
– 100% aluminum joinery was installed in part B of the building (including the vestibule)
– The staircase lighting lamps are being installed in part B of the building
– The attic insulation has been completed with mineral wool and the attic casing with a plasterboard on the frame in part A of the building
– The plastering of walls and ceilings in the premises has been completed. Ground floor – 3rd floor in part A of the building
– The surfaces of walls and ceilings in flats in part A of the building are primed with paint
– Currently, finishing works are underway (plastering, plasterboard structures) in the staircase in part A of the building
– Entrance doors to the premises in part A of the building have been installed
– Balcony railings were installed in part A of the building
– The painting of the facade of part A of the building has been completed
– Resin coatings were made on balconies on the level of 1-3 floors of the building and in the garbage can in part A of the building
– The assembly of the elevator in part A of the building has been completed (procedures for the elevator acceptance by UDT are in progress)
– Installation of local heaters in apartments in part A of the building is in progress
– White electrical assembly in the apartments in part A of the building is in progress
– Water and sewage works completed. , What. and hydrant installation
– Performance tests of hydrants in the garage were carried out with a positive result
– Lighting of the garage and the entrance to the garage was made (target lamps with motion sensors installed)
– The entrance gate to the garage has been installed
– Works related to the development of the area around the buildings have been started (i.e. paving works – sidewalks, bands; greenery works – surface drainage of the ceiling above the garage, rain drains, geotextiles, fertilization of fertile soil, fencing works)
– Porcelain floors in the staircase were made, along with the facing of stair steps and the arrangement of pedestals in part B of the building
– Water meters and heat meters have been installed in water and sewage installation risers and what in part B of the building
– The assembly of the elevator has been completed, preparations are underway for acceptance by the Office of Technical Inspection in part B of the building
– The external facade of part B of the building was cleaned, primed and painted
– Residential changes related to bricklaying partition walls in part A of the building have been completed
– Water and sewage installations completed. and what. in apartments in part A of the building
– Installation of electrical installations inside the premises in part A of the building has been completed
– Cement screeds on the 3rd floor have been completed. – Ground floor in part A of the building
– Finishing works of the premises are in progress – plastering ceilings and walls, making window frames from plasterboard, etc. in part A of the building
– The attic is partially insulated with mineral wool along with the installation of the frame for the construction of the plasterboard in part A of the building
– Installation of an elevator in progress – a passenger lift in part A of the building
– An energy connection with a cable connection has been made. Final acceptance by the Power Plant is in progress
– Troughs and power cables have been laid for the Main Switchboard in the garage from the cable connection
– Insulation of the walls of staircases in the garage with mineral wool along with spraying with thin-layer plaster
– Insulation with polystyrene has started from the bottom of the projecting parts of building A and the connector
– A rainwater flow regulator was installed in the external rainwater well
– External balcony railings were installed in part B of the building
– Roofing works have been completed – roofing with aluminum sheet with flashings, gutters and downspouts in part B of the building
– An external lightning protection system was installed in part B of the building
– A set of accessories was installed on the roof, such as fans, air vents, lightning protection masts, chimney sweeps, snow guards and a roof hatch in part B of the building
– Entrance doors to the premises in part B of the building have been installed
– The filling of internal walls and GK constructions in part B of the building has been completed
– The putty walls were painted with white priming paint in the apartments in part B of the building
– The aluminum door of the main entrance to part B of the building has been installed
– Local heaters were installed in part B of the building
– Roofing with aluminum sheet in part A of the building has been completed
– Sheet metal work, gutters and downspouts in part A of the building were completed
– An external lightning protection system with lightning protection masts was installed on the roof in part A of the building
– A set of accessories was installed on the roof, such as fans, exhaust vents, roof hatch, chimney sweeps and snow guards in part A of the building
– Water and sewage risers were made. in part A of the building
– Mechanical ventilation risers in part A of the building
– Partition walls of the ground floor, 1st floors, 2 floors, shafts and bathrooms, 3 floors and attic in part A of the building were built
– Water and sewage installation work has commenced. And what. in apartments in part A of the building
– Electrical works have commenced in the apartments in part A of the building
• The foundation slab is concreted
• Garage walls are being built
• The excavation under building A is completed
• A square timber band in the Berlinka-type wall is made
• The entire excavation was secured
• A layer of lean concrete has been made
• The construction of foundation wells is in progress